AKTOR Begins Drilling Homorod Tunnels on Brașov-Sighișoara Railway

0

Get real time updates directly on you device, subscribe now.

AKTOR, the constructor of the section, begins the drilling of the northern pair of tunnels, called Homorod, with a length of 5.1 km each, by starting the third tunnel boring machine (TBM) in place, in a location just 4 km west from Racoș (location). Last week, Alexandra started the works for piercing this second pair of tunnels in the mountains around Racoș. At this moment, TBM 3, Alexandra, is already partially inside the mountain.

This is one of the few projects in Europe where four TBMs are drilling as many tunnels at the same time.

The tunnels are on the thread of the future Brasov-Simeria railway line, part of the Rhine-Danube Corridor, Brasov-Sighisoara section, subsection 2: Apața-Cața. The project is co-financed by the European Union, and the contract was signed by the National Railway Company (CFR SA) with the consortium of AKTOR SA – Alstom Transport SA – Arcada Company.

“We are proud to mark this significant milestone in this critical part of the Brasov-Sighisoara railway project. This progress underscores our commitment to delivering state-of-the-art infrastructure projects that enhance connectivity across Romania and the wider European region. By utilizing advanced technologies such as Tunnel Boring Machines, we are increasing the efficiency and safety and minimize the external impact. These tunnels will play a crucial role in strengthening the Rhine-Danube Corridor, contributing to the region’s sustainable growth and mobility for generations to come”, Alexandros Exarchou, Chairman of the Board of Directors and CEO of Aktor Group, stated.

The first two TBMs which are currently drilling the southern tunnel from Racoș on the opposite direction, towards Apața, to create the first pair of tunnels with a length of 6.9 km, are already deep inside the mountain. They already overpassed 1.2 tunnel kilometers: Eleni, which was started in early March, already bore 700 meters and Varvara, started in late May, bore 500 meters. Eleni and Varvara have a remarkable length: Eleni is approximately 105 meters long, and Varvara is approximately 84 meters long, meaning they now operate in pitch black conditions, inside the mountain.

In the tradition created with the first two TBMs, the third TBM to begin drilling towards Homorod has been baptized Alexandra. Alexandra has as well an impressive length of 103.00 meters.

As they progress inside the mountain, the TBMs mount around them pre-cast concrete segments 1.5 meters wide each, like a ring, to create the circular shape of the tunnel.

Sotirios Koropoulis

The process of installing a TBM and starting the drilling operation is complex and requires detailed planning, preparation, and execution. By using TBMs, we can construct tunnels with greater precision, safety, and environmental consideration than traditional methods allow. This innovative approach to tunnel construction opens new possibilities for developing infrastructure while minimizing the impact on the surrounding area”, explains Sotirios Koropoulis, the Project Director for the Apața-Cața section, Lot 2 construction site.

The tunnels will be connected by galleries: 13 connecting galleries, with a total length of 601 linear meters for the Ormeniș tunnel, respectively 10 connecting galleries, with a total length of 417 linear meters for the Homorod tunnel.

The Ormeniș/Homorod underpasses will each consist of two railway tunnels with one railway line each. The distance between the two bored tunnels will be variable and is planned to be between 30m near the entrance areas and 70m near the high overburden area.

The four tunnels will have an inner diameter of 8.6 meters (an outer diameter of 9.4 meters, due to the concrete lining). The four TBMs used by Aktor have been built by the HERREKNECHT company. A TBM can drill large-scale tunnels with an average of 10-15 meters per day, six days per week, and one day of maintenance.

DONATE: Support our work
In an ever changing and challenging world, the media is constantly struggling to resist. Romania Journal makes no exception. We’ve been informing you, our readers, for almost 10 years, as extensively as we can, but, as we reject any state funding and private advertising is scarce, we need your help to keep on going.
So, if you enjoy our work, you can contribute to endorse the Romania Journal team. Any amount is welcome, no strings attached. Choose to join with one of the following options:
Donate with PayPal
Donate by Bank Wire
Black Zonure SRL
UniCredit Bank. Swift: BACXROBU
RON: RO84 BACX 0000 0022 3589 1000
EURO: RO57 BACX 0000 0022 3589 1001
USD: RO30 BACX 0000 0022 3589 1002

Leave A Reply

Your email address will not be published.