New subway section in Bucharest operational as of H2 2018
Bucharesters will be able to take the subway on a new line as of the second half of 2018, Metrorex director Marin Aldea announced on Thursday
The new section is Valea Ialomitei-Eroilor of the Drumul Taberei subway line 5.
Trains from the existing fleet will go ont his new line, but the public metro company vows to buy other 13 new ones. According to the director, the acquisition procedure will take about one year and a half.
The works on the subway line 5 are 90% concluded on the structure and about 45% of the finishing works.
“We aim to conclude the structure works by the end of this year and the finishing works in the first half of 2018,” Aldea said.
As for the works on the Eroilor-Iancului-Pantelimon line, an official with the Transport Ministry announced they will start by the end of this year.
On Thursday, the tunneling boring machine-TMB, baptized St. Filoftea, came to the surface, an event marking the completion of the excavation works on the Râul Doamnei-Eroilor subway section.
On line 2, the TMB dug almost 4.4 kilometers of tunnel linking the Line 1-3 to Line 5.
DONATE: Support our work
In an ever changing and challenging world, the media is constantly struggling to resist. Romania Journal makes no exception. We’ve been informing you, our readers, for almost 10 years, as extensively as we can, but, as we reject any state funding and private advertising is scarce, we need your help to keep on going.So, if you enjoy our work, you can contribute to endorse the Romania Journal team. Any amount is welcome, no strings attached. Choose to join with one of the following options:
Donate with PayPal
Donate by Bank Wire
Black Zonure SRLUniCredit Bank. Swift: BACXROBU
RON: RO84 BACX 0000 0022 3589 1000
EURO: RO57 BACX 0000 0022 3589 1001
USD: RO30 BACX 0000 0022 3589 1002